Volume 2024, Issue 1 1244075
Research Article
Open Access

Stochastic Optimal Reconfiguration and Placement of Photovoltaic Systems in Distribution Networks: A Real Case Study

Mohammad Najafi

Mohammad Najafi

Department of Electrical Engineering , Tafresh University , Tafresh , 39518-79611 , Iran , tafreshu.ac.ir

Search for more papers by this author
Mohammad Reza Miveh

Corresponding Author

Mohammad Reza Miveh

Department of Electrical Engineering , Tafresh University , Tafresh , 39518-79611 , Iran , tafreshu.ac.ir

Search for more papers by this author
First published: 01 August 2024
Citations: 4
Academic Editor: Akshay Kumar Saha

Abstract

In this paper, a stochastic multi-objective (MO) modeling for the optimal reconfiguration and placement of photovoltaic (PV) systems in distribution networks (DNs) is presented. The main objectives are to jointly maximize the profit of generating companies (GenCos) as well as to minimize the distribution company’s (DisCo) costs and the expected interruption cost (ECOST). This approach can provide numerous economic and technical advantages for all players in the restructured power system, including GenCos, DisCos, and customers. To attain more practical and accurate results in the simultaneous placement of PVs and reconfiguration, uncertainties are considered in the problem formulation. To cope with the stochastic behavior of PV systems, electricity prices, and demands in the DN, the scenario approach is used. The proposed optimization problem is solved by the dragonfly algorithm (DA) and the best compromise solution is chosen using a fuzzy satisfying criterion. The results are also compared with the particle swarm optimization (PSO) algorithm. To confirm the effectiveness of the proposed MO model, it is implemented on the IEEE 33-bus DN and simulated in various case studies. The model is also applied to a real DN. The results confirm that the proposed model gives a more desired schedule than previous approaches, as all players in the DN including the PV owners, DisCo, and customers are satisfied at the same time.

1. Introduction

Recently, researchers have shown an increased interest in using distributed energy resources (DERs) such as wind and photovoltaic (PV) systems in distribution networks (DNs) [1, 2]. In addition, power quality and reliability improvements can be achieved for the customers by proper integration of DERs [3]. However, DNs can face serious security challenges, if DERs cannot appropriately and optimally integrate into the network. Accordingly, optimal sitting/sizing of DERs in the DN plays an important role in increasing the security, power quality, and reliability of the power system and reducing the costs of distribution companies (DisCos) [4]. Moreover, solving this optimization problem can lead to reducing customer interruption costs and increasing DER owners’ profit in a deregulated power system. To date, various methods have been developed and introduced for optimal sitting/sizing of DER based on single-objective (SO)/multi-objective (MO) functions [5, 6, 7, 8, 9]. Moreover, optimal sitting/sizing of DER along with optimal network reconfiguration has received critical attention due to high performance and efficiency [10].

Recent advances in the electricity industry have brought many benefits to grid operators and other players of DNs. Distribution network reconfiguration is one of the best tools to address the problem of DNs [11]. It is a problem in which the open/close conditions of switchable ties are determined to attain optimal configuration. The most important benefits of reconfiguration are the reduction of losses and improvement of voltage profile as well as reliability. Therefore, optimal distribution network reconfiguration can be introduced individually as a critical optimization problem to improve the power quality and reliability of DNs. Nevertheless, simultaneous optimal sitting/sizing of DER and network reconfiguration can provide more advantages for DER owners by changing the switch conditions in such a way that more power can be supplied to the consumers [10].

1.1. Literature Review

The optimal sitting/sizing of DER with optimal network reconfiguration as a separate optimization problem in DN is the best solution for coping with the challenges stemming from the high penetration of such sources. In [12], a MO reconfiguration for enhancing the voltage profile, reducing real power losses, and improving the voltage unbalance index for a DN is suggested based on the fast nondominated sorting genetic algorithm. Niknam [13] proposed a MO reconfiguration based on honey bee mating optimization to reduce the number of switching operations, and the real power loss and to improve the voltage profile. To minimize the loss of large-scale distribution systems, a system reconfiguration is also presented in [14]. Mazza et al. [15] offered an optimal MO reconfiguration for a distribution network to reduce energy not supplied (ENS) and power loss. The major drawback of this study is that the objective function is optimized only from DisCo’s viewpoint. In [16], an optimal reconfiguration for a real feeder is investigated. In a similar study, Ahuja et al. [17] suggested a MO reconfiguration. A MO reconfiguration using the discrete particle swarm optimization is proposed in [18]. Reduction of power loss, the number of switching operations, and enhancement of voltage profile are the main objectives of this paper. In [19], a reconfiguration method to reduce active power losses and improve the reliability index using the Ԑ-constraint is presented. A runner-root algorithm is used to cope with system reconfiguration in [20].

Several papers have been published on the joint optimal placement of DERs and system reconfiguration. In [10], the authors use system reconfiguration in the presence of DERs for power loss reduction and load restoration improvement. In [21], a method is suggested for optimal network reconfiguration in radial distribution networks with DERs to increase the load balance factor index and reduce power loss. A MO reconfiguration using an enhanced gravitational search algorithm for radial systems considering DERs is presented in [22]. In [23], using mixed-integer linear programing (MILP), the reconfiguration issue in the distribution network in the presence of DERs is investigated. The loss reduction from the DisCo view is the only objective of this paper. In another major study, Nikkhah and Rabiee [24] suggested a long-term planning model for a hybrid system in which the grid voltage stability is considerably improved.

In [25], in addition to considering reliability and power quality issues from the DisCo view, the cost of DERs from the distributed generation (DG) owners’ point of view is optimized using the PSO. The PSO is also used for dynamic and static reconfiguration with the optimized allocation of PV-DG and storage systems in [26]. Adaptive GA is employed to optimize the allocation of DERs in the DN considering uncertainties for loads and generations in [27]. In [28], the optimal network reconfiguration considering DERs is presented to reduce power and operation costs as well as to improve the voltage profile. In the same vein, Nasiraghdam and Jadid [29] presented the optimal network reconfiguration considering DERs using the artificial bee colony algorithm. Reconfiguration of DNs in the presence of DERs is done using the PSO algorithm in [30], to achieve an improved voltage profile and minimize switching operation costs. A joint feeder reconfiguration and optimal sizing method for DERs using the teaching–learning algorithm is proposed in [31]. In this study, ENS, power loss, and voltage profile are optimized only from the DisCo view. An optimal network reconfiguration with the presence of DERs to improve the distribution grid hosting capacity using a linearized power flow model is proposed in [32]. In [33], the optimal DG allocation and network reconfiguration are optimized considering probabilistic loads and DGs to enhance the voltage stability and loss profile. In [34], an optimization method is suggested for the dynamic feeder reconfiguration problem in the distribution system over multiple time intervals considering DERs. In another major study, Lotfi et al. [35] suggested a MO framework for feeder reconfiguration along with capacitor allocation problems over multiple time intervals considering DERs. A network reconfiguration and allocation of capacitor units in a radial distribution system using an enhanced artificial bee colony optimization is also proposed in [36]. In [36], the MO problem is considered as a combination of ENS and emission produced by DG units and grid; moreover, network loss is defined as the other objective function.

For better comparison, a summary of the abovementioned papers is given in Table 1. As can be seen, remarkable papers either separately or jointly have been published on DG sitting/sizing and network reconfiguration. However, the optimal sitting/sizing of DGs with network reconfiguration at the same time is not considerably taken into account due to the complexity of the problem. As stated before, it is required to take into account the influence of intermittency of DERs such as PV systems, the fluctuations in load demand, and electricity price in system reconfiguration. As can be observed in Table 1, very few studies have investigated the impact of uncertainties of electricity price, load as well as DERs at the same time. Furthermore, most of the MO optimization models presented in the above literature have been investigated only from DisCo’s point of view. It is apparent from the table that very few papers are focused on optimization models from DG owners’ or customers’ perspectives. However, there appears to be an absence of an MO optimization model for optimal sitting/sizing of DGs and network reconfiguration from DisCo’s, generating companies (GenCos), and customers’ points of view, simultaneously.

Table 1. Comparison between the existing papers and the proposed approach.
References Objective Reconfiguration DG Uncertainty Objectives
O1 O2 R1 DG1 DG2 DG3 U1 U2 U3 A1 A2 A3 A4 A5
[12]
[13]
[14]
[15]
[16]
[17]
[18]
[19]
[20]
[21]
[22]
[23]
[24]
[25]
[26]
[27]
[28]
[29]
[30]
[31]
[32]
[33]
[37]
[35]
[36]
Proposed method
  • O1, multi-objective; O2, single-objective; R1, considering reconfiguration; DG1, the attendance of DGs; DG2, optimal DG sizing; DG3, optimal DG siting; U1, demand uncertainty; U2, DERs uncertainty; U3, price uncertainty; A1, loss minimization; A2, reliability enhancement; A3, voltage profile enhancement; A4, DisCo’s cost minimization; and A5, DG owner’s profit maximization.

1.2. Contributions and Paper Organization

This study suggests an optimal probabilistic MO network reconfiguration along with the sitting/sizing of PV systems in a DN. The impact of uncertainties in electricity price, loads, and PV systems is considered using a scenario-based approach. The suggested method jointly minimizes the cost of the DisCo, and expected interruption cost (ECOST) and maximizes the profit attained by the PV owners as GenCos. The optimization problem is solved using the dragonfly algorithm (DA) and compared with the PSO algorithm. The major contributions of the present paper are as follows:
  • (i)

    The optimal reconfiguration model for a restructured distribution network is suggested with the economic aims from PV owners’, DisCo’s, and customers’ perspectives.

  • (ii)

    The scenario method is used to deal with the uncertainties of loads, PV output, and electricity price.

  • (iii)

    The sitting/sizing of PV systems in the DN is optimized using the proposed stochastic MO model.

  • (iv)

    The proposed optimization problem is solved by the DA and the best compromise solution is chosen using fuzzy satisfying criterion.

  • (v)

    The model is implemented on a standard test system and a real DN in various case studies.

The study is organized as follows. Section 2 describes the uncertainty modeling. Section 3 presents the problem formulation. The DA is described in Section 4. Simulation results are provided in Section 5. Finally, the conclusion is given in Section 6.

2. Uncertainty Modeling

PV systems have received great attention in Iran in recent years due to numerous advantages such as high availability of sunlight and cleanliness. However, the output power of PV systems considerably depends on solar radiation, thereby requiring the modeling of the solar system probabilistically. In other words, the output power of PV systems is intermittent owing to solar radiation variation. Owing to several reasons such as environmental conditions, time of day, month, season, and the orientation of the PV arrays to the sun radiation, there is a high degree of uncertainty in solar radiation. The solar radiation can be modeled with the beta distribution as follows [38]:
(1)
where α and β are, respectively, the beta distribution shape and scale factors (W/m2) and R is solar radiation (W/m2).
In this paper, the solar variation is separated into several scenarios to provide multistate variable modeling. The following equations have described the probability of each scenario [38]:
(2)
(3)
where πPV and RPV are the probability and mean value of solar radiation at the Rth scenario. In addition, Rf,PV and Ri,PV denote the ending and starting point.
The power generation of a PV system can be also written as follows:
(4)
where PPV, PPV,r, RSTD, and Rc are output power of the PV power generation (MW), rated power of the PV power generation (MW), solar radiation in the standard radiation, which normally is set to 1,000 W/m2, and a certain radiation point typically is set to 150 W/m2, respectively.
The typical radiation power curve for a PV system in Iran and the solar radiation probability density function (PDF) of the typical day are extracted from Aien et al. [39]. In addition, for power system planning studies, it is required to model the load demand probabilistically. Normal PDF is one of the most common ways to model the uncertainty of the load demand. Using the historical data achieved from the load consumption, the PDF of the load can be approximated similarly to the solar radiation. In the scenario-based method, the probability and demand for various scenarios can be written as follows:
(5)
(6)
where μ and σ are mean and variance of load. Also, πl and are the probability and demand of the lth load scenario in the interval from to .
Similar to solar radiation and load, market price uncertainty plays an important role in optimal PV allocation and reconfiguration. In this regard, the uncertainty of the electricity price is modeled based on three scenarios as presented in [40]. To obtain the mixed probability scenarios of the PV, load, and price, several scenarios can be joined by multiplying the probabilities as follows:
(7)
where πPV, πl, and πp are the probability scenarios PV, l, and p of the PV, load, and price, respectively.

3. Problem Formulation

The competition among different entities in a deregulated environment such as DisCos, PV owners GenCos, and consumers can give many advantages to the power system. In a deregulated power system, DisCos are the owner and operator of the distribution system, which are responsible for buying wholesale electricity either from the upstream market or through direct contracts with GenCos and supplying electricity to the customers. The main objectives of the DisCos are reducing the distribution cost and enhancing the distribution network performance. In addition, a customer is an entity that buys the required electricity demand from DisCos. Therefore, the DN has the responsibility to provide uninterruptible power for the consumer to improve the reliability of the whole power system. On the other hand, a GenCo is an owner–operator of one or more power plants and DGs that sell electricity to the network. The profit of the owners of PVs can be maximized by selling more electricity to the DN. As mentioned above, each of the entities including DisCos, GenCos, and consumers has a unique benefit, but they may have conflicted relationships. Hence, the main aim of this paper is to suggest an optimal network reconfiguration and DGs sitting/sizing at the same time using economic MO functions to reach a trade-off among the three mentioned entities.

3.1. Objective Functions

In this part, three objective functions are presented to model DisCo’s cost, ECOST, and PV owners’ profit as follows.

3.1.1. PV Owners’ Profit Maximization

As PV owners are not in charge of the security constraints of the DN, only two costs containing the expected maintenance cost as well as the expected income are considered in the modeling. For the sake of simplicity, the expected maintenance cost, including monitoring and washing costs of PV power generation is neglected here. In Iran’s power market, PVs sell energy to DisCos through direct contracts; therefore, the uncertainty in the electricity price of PV owners is not considered. Consequently, the expected income of the PV owner can be expressed as follows:
(8)
where is the active power of PV connected to bus i in scenario s and is the contract price of PV systems placed at bus i ($/MWhr). Moreover, κs and κPV are set of all possible scenarios and PVs installed in buses.
Therefore, the objective function to optimally allocate PVs in the DN from the owner’s point of view can be achieved as follows:
(9)
where is the expected profit of PV owners.

3.1.2. DisCo’s Cost Minimization

DisCo is responsible for operating the DN properly by considering all security and operational constraints as well as providing the required power for the customers. Generally, the costs of DisCos include the expected cost of buying energy from the upscale grid and the expected cost of electricity provided through direct contracts with DG owners. As there exists a limitation in generating power with DGs such as PV systems, the DisCo must procure the needed electricity from the upstream market. However, the price of electricity procured through the upscale market is different from the electricity price of PV systems and contains uncertainties. The expected cost of DisCo can be modeled stochastically as follows:
(10)
where is the active power inserted from the substation to bus i in scenario s and is the electricity price at scenarios.
It should be noted here that the cost of power bought from the PV owners is already given in Equation (8). In addition, the price of electricity bought through PV owners has been modeled deterministically. Consequently, the objective function to optimally allocate PVs in the DN from the DisCo’s point of view can be formulated as follows:
(11)
where is the expected cost of DisCo.

3.1.3. ECOST Minimization

To improve the reliability of the DN, the minimization of the ECOST is also considered as the objective function. Assessing ECOST gives the ability to planners and engineers to achieve a satisfactory level of reliability for end-users and improve suitable operation strategies. The following equation can be used for the calculation of the ECOST at bus i [37]:
(12)
where Lij is the power of interruption by losing line ij (kW), C is the cost of interruption ($/MW), which has a constant value equal to 50 $/MW, λij is the expected failure rate of the DN equipment, and κl is the set of lines (branches). It should be noted that the section with the highest impedance has the biggest failure rate of 0.5 f/year and the section with the smallest impedance has the least failure rate of 0.1 f/year.
Before PV installation, each feeder between i and j contains an uncompensated failure rate of . If the feeder branch is completely compensated, the corresponding failure rate decreases to . If components of the current are not fully compensated, a failure rate is presented with a linear link to the percentage of compensation. Therefore, the compensation coefficient of the ith branch can be given as follows:
(13)
where , and , are the reactive/active components of the ith branch current after/before compensation, correspondingly. The new failure rate of the ith branch is calculated as follows:
(14)
where in the above equation :
(15)
where is the expected interruption cost.

3.2. Constraints

To achieve optimal values for the objective functions, the optimization problems in the power system have specific constraints. In this study, the following constraints are defined for the proposed model.

3.2.1. Radial Constraints

The radial structure offers many advantages for DNs such as the simple protection scheme and low short circuit current. Therefore, it is necessary to maintain the network structure radially after any change in the DN. Based on the graph theory, the structure of a DN remains radial, if the number of closed switches is equal to the number of nodes minus one. This network’s radially constraints can be defined as (γij = γji, ∀i, jκl):
(16)
where γij is the decision variable that can be 1 (closed) or 0 (open). Nl is the total number of system branches.

3.2.2. Branch Capacity Limit

One of the most important limitations of distribution lines is the current that is delivered through lines and can be defined as follows:
(17)

The above constraints indicate that for the line ij including a closed switch, the current of the line is lower than its maximum limit.

3.2.3. Voltage Profile

The safe operation limits for the voltage of buses also can be given as follows:
(18)

3.2.4. PV Power Generation Limit

The generation of PV units is limited as follows:
(19)

3.2.5. Limitation on the Maximum Number of PVs

In order to solve problems such as stability difficulties with high DG penetration, the number of these resources must be limited based on their size and number:
(20)
where NPV is the maximum number of permissible PVs for installation in the DN. is the binary variable for modeling the location of the PV system at bus i.

Using this constraint and the PV power generation constraint, the optimal sitting/sizing of PV systems can be attained with optimal reconfiguration.

4. Dragonfly Algorithm (DA)

Here, the DA is used for solving the MO optimization problem. The main reason behind choosing this algorithm is that it can improve the initial random population for a given problem, converge toward the global optimum, and provide very competitive results compared to conventional algorithms. In addition, it can find very precise approximations of Pareto optimal solutions with high uniform distribution for MO problems.

The DA is a swarm intelligence optimization method initiated by the static and dynamic swarming behaviors of dragonflies, which was first reported by Mirjalili [41]. Swarm intelligence and the particular behavior of dragonflies are the main factors in developing this type of metaheuristic algorithm. Two crucial stages of optimization, including exploration and exploitation, are planned by modeling the social interaction of dragonflies in navigating, finding foods, and escaping enemies when swarming dynamically or statistically. A group of dragonflies with small directions and velocity hunting the prey in a small area are static swarm dragonflies. On the other hand, a variety of dragonflies with the ability to travel long distances in constant directions are called the dynamic swarm. Normally, two vectors including step (DX) and position (X) are applied to update the position of dragonflies in a search space and simulate their movements. The modeling of the DA can be presented in five steps as follows:

Separation: This refers to the avoidance of any static collision between dragonflies.

Alignment: It indicates that the velocity of individual dragonflies matches the velocity of other dragonflies in the neighborhood.

Cohesion: It refers to the tendency of individuals to the center of the mass of the neighborhood.

Attraction: it refers to being attracted to the food source.

Distraction: It refers to an escape from the enemy.

The combination of all five mentioned motions reflects the behaviors of dragonflies. More details about this algorithm can be found in [41].

The mentioned steps can be modeled mathematically as shown below.

The separation can be modeled as:
(21)
Alignment can be written as follows:
(22)
The cohesion can be modeled as follows:
(23)
Attraction toward a food source can be presented as follows:
(24)
Distraction outwards an enemy can be given as follows:
(25)
where X indicates the position of the current individual, Xj shows the position jth neighboring individual, and N is the number of neighboring individuals, X+and X indicate the position of the food source and enemy, respectively.

The flowchart of the proposed method is depicted in Figure 1.

Details are in the caption following the image
The flowchart of the proposed method.

5. Simulation Results

To confirm the effectiveness of the proposed model, two different systems including the IEEE 33-bus system and a real DN in Iran are considered and simulated in various cases. In both systems, the stochastic MO model is solved using the DA. In the following subsections, numerical results are provided for both test systems.

5.1. Numerical Results for IEEE 33-Bus DN

The single-line diagram of the IEEE 33-bus DN contains 37 branches, 32 sectionalizing switches, and five tie switches, as depicted in Figure 2 [42]. The suggested model is simulated in the MATLAB software package, which can solve the optimization problem. The model is optimized by the DA and compared with the PSO. Table 2 depicts the PV-demand-price scenarios of uncertain parameters. For straightforwardness, a single point is considered an operation horizon. It can be extended to a multipoint horizon. Three PV systems are assumed to be dispatched in the test network with a capacity of 1.2 MW for each PV system. As seen, three scenarios for the price of electricity are considered to be paid to the utility grid as $42, $46, and $50. It should be noted that the contract price of PV systems is taken into account as $50 as the transmission cost within the network is ignored. This type of contract with a high price can attract more private investors to install more renewable sources. This paper does not address the uncertainties in the price of electricity for PV systems. In other words, the price of purchasing power from PVs is considered to be fixed as there exists no cost of transmission for the PV units. In the electricity market of Iran, the network policy-makers buy the generated power of PVs at a fixed and attractive price to provide significant profits and support private investors for them. Moreover, to model the load uncertainties, three various scenarios are considered. The solar radiation scenarios of PV systems are also shown in Table 2.

Details are in the caption following the image
The one-line diagram of IEEE 33-bus DN.
Table 2. PV–load–price scenarios and their probabilities.
Scenario number ($/MWhr) PDl (%) RPV(%) πs
s1 50 0.95 0 0.015126
s2 50 0.95 0.25 0.00348
s3 50 0.95 0.5 0.002556
s4 50 0.95 0.75 0.004071
s5 50 0.95 1 0.004764
Price scenario: s6 50 1 0 0.070588
($/MWhr) πp s7 50 1 0.25 0.01624
P1 50 0.2 s8 50 1 0.5 0.011928
P2 46 0.6 s9 50 1 0.75 0.018998
P3 42 0.2 s10 50 1 1 0.022232
s11 50 1.05 0 0.015126
s12 50 1.05 0.25 0.00348
s13 50 1.05 0.5 0.002556
s14 50 1.05 0.75 0.004071
s15 50 1.05 1 0.004764
  
s16 46 0.95 0 0.045378
s17 46 0.95 0.25 0.01044
s18 46 0.95 0.5 0.007668
s19 46 0.95 0.75 0.012213
Solar radiation scenario: s20 46 0.95 1 0.014292
RPV (%) πPV s21 46 1 0 0.211764
R1 0 0.4726 s22 46 1 0.25 0.04872
R2 0.25 0.1087 s23 46 1 0.5 0.035784
R3 0.5 0.0798 s24 46 1 0.75 0.056994
R4 0.75 0.1272 s25 46 1 1 0.066696
R5 1 0.1488 s26 46 1.05 0 0.045378
s27 46 1.05 0.25 0.01044
s28 46 1.05 0.5 0.007668
s29 46 1.05 0.75 0.012213
s30 46 1.05 1 0.014292
  
s31 42 0.95 0 0.015126
s32 42 0.95 0.25 0.00348
s33 42 0.95 0.5 0.002556
s34 42 0.95 0.75 0.004071
s35 42 0.95 1 0.004764
Load scenario: s36 42 1 0 0.070588
PDl (%) πp s37 42 1 0.25 0.01624
P1 0.95 0.16 s38 42 1 0.5 0.011928
P2 1 0.68 s39 42 1 0.75 0.018998
P3 1.05 0.16 s40 42 1 1 0.022232
s41 42 1.05 0 0.015126
s42 42 1.05 0.25 0.00348
s43 42 1.05 0.5 0.002556
s44 42 1.05 0.75 0.004071
s45 42 1.05 1 0.004764

5.1.1. Case 1: SO Reconfiguration Aiming to Maximize PV Owner’s Profit

In this case study, the main objective is to maximize the profit of PV owners. The results including the profit of PV owners, PV placement, and the reconfiguration are shown in Table 3. As seen, the profit of PV owners using the DA is $59.9. The cost of the DisCo in this case is $191.563. As can be observed, PV systems are installed at buses 30, 31, and 32, and switches L6−7, L9−10, L12−13, L15−16, and L28−29 are opened in the test system. The installed PVs are not close to the substation and only supply the nearby buses. Moreover, the injection power of PV systems optimized by the proposed DA in all scenarios is depicted in Figure 3. As can be observed, the power generation of PVs is zero in some scenarios, and it is nonzero in most scenarios with the available capacity.

Table 3. Profit of PV owners, optimal placement of PV units, and reconfiguration in Case 1.
Optimization method Profit of DG owners ($) PV placement Opened switches
PSO 59.9 B30, B31, B32 L6−7, L9−10, L12−13, L15−16, L28−29
DA 59.9 B30, B31, B32 L6−7, L9−10, L12−13, L15−16, L28−29
Details are in the caption following the image
Power generation with PVs optimized with the DA in Case 1.

5.1.2. Case 2: SO Reconfiguration Aiming to Minimize DisCo’s Cost

Here, it is aimed to minimize the cost of energy bought from both PVs and the upscale grid. Using this objective, the DisCo pays the lowest money to the PV owners and the upscale grid. The cost of DisCo, optimal PV placement, and network reconfiguration optimized with the DA and PSO, in this case, are presented in Table 4. As seen, the cost of DisCo is considerably reduced in comparison with Case 1. The profit of PV owners is also $11.3748, which its value is notably reduced in comparison with Case 1, due to the changing of the objective function. The ECOST is also equal to $213.49, which is very high. As seen in Table 4, PV systems are installed at buses 6, 12, and 16 in both algorithms. A comparison of Cases 1 and 2 shows that by changing objective functions the location of PVs and network reconfiguration can be changed. Furthermore, the injection power of PV units optimized by the DA is illustrated in Figure 4. As observed, the provided energy by PVs is considerably reduced in this case as the purchased energy from PVs is based on an expensive fixed price that is higher than the utility grid price. The results confirm that the appropriate PV placement and optimal reconfiguration can reduce the costs of DisCos. It is clear that in this case, the power losses of the network are inherently reduced.

Table 4. Disco’s cost, optimal location of PV units, and reconfiguration of the IEEE 33-bus in Case 2.
Optimization method Disco’s cost ($) PV placement Opened switches
PSO 177.37 B6, B12, B16 L7−8, L9−10, L14−15, L32−33, L25−29
DA 177.37 B6, B12, B16 L7−8, L9−10, L14−15, L32−33, L25−29
Details are in the caption following the image
Power generation with PVs optimized with the DA in Case 2.

5.1.3. Case 3: SO Reconfiguration Aiming to Minimize the ECOST

In this part, the main objective is to minimize the ECOST. Minimizing ECOST empowers the planners to select the adequate class of reliability for end-users and develop proper operation policies with low cost. The jointly optimal PV placement and network reconfiguration are optimized with the DA and compared with the PSO to minimize the ECOST. Table 5 gives the ECOST, optimal PV placement, and reconfiguration with both algorithms. The profit of PV owners and the cost of the DisCo, in this case, are $55.9 and $186.38, which varies with Cases 1 and 2. Here, the locations of PVs and configuration are changed such that the interruption cost of customers is minimized to $154.2. In addition, the injection power of PV systems optimized by used algorithm is explained in Figure 5. As seen, the purchased energy through PVs is significantly increased in this case to minimize the ECOST. As observed from the results, the ECOST can be minimized by optimal reconfiguration and PV placement at the same time.

Table 5. ECOST, the optimal location of PV units, and reconfiguration of IEEE 33-bus in Case 3.
Optimization method ECOST ($) PV placement Opened switches
PSO 155.1 B30, B31, B32 L6−7, L9−10, L12−13, L15−16, L28−29
DA 154.2 B16, B17, B18 L7−8, L10−11, L14−15, L17−18, L28−29
Details are in the caption following the image
Power generation with PVs optimized with the DA in Case 3.

5.1.4. Case 4: MO Reconfiguration Aiming to Maximize PV Owner’s Profit and Minimize ECOST

In this part, the Pareto front is attained for the suggested model to optimize the PV owner’s profit and minimize the ECOST. Figure 6 shows the Pareto optimal front achieved for this case study. Table 6 also presents the Pareto results based on the best compromise solution, which is achieved using the min–max fuzzy satisfying method introduced in [43]. As seen, the best trade-off result with the DA is related to solution#3, which is equal to 1.06. For the best result in solution#3, the PV systems are installed at buses 28, 32, and 33, and switches L7−8, L9−10, L14−15, L16−17, and L28−29 are opened, as depicted in Table 7. The maximum PV owner’s profit and the minimum ECOST optimized with the DA and PSO are also given in Table 7. The cost of DisCo in this case is equal to $180.87. The injected power of PV systems optimized by the DA is given in Figure 7.

Details are in the caption following the image
Pareto optimal front of MO problem in Case 4.
Table 6. Pareto optimal results in Case 4.
Solution# Ψ1 ($) Ψ2 ($) Sum (, )
PSO
 1 36.52 188.02 1.00 0.00 1.00
 2 36.26 187.02 0.89 0.13 1.02
 3 35.42 183.59 0.53 0.58 1.11
 4 34.18 180.36 0.00 1.00 1.00
 5 36.52 188.02 1.00 0.00 1.00
DA
 1 59.28 182.68 1.00 0.00 1.00
 2 56.68 181.55 0.81 0.09 0.91
 3 51.99 181.46 0.80 0.26 1.06
 4 49.93 177.83 0.21 0.33 0.54
 5 40.14 177.79 0.20 0.68 0.88
 6 31.24 176.56 0.00 1.00 1.00
 7 59.28 182.68 1.00 0.00 1.00
  • The best trade-off result.
Table 7. PV owner’s profit, ECOST, optimal placement of PV units, and reconfiguration Case 4.
Case 4 PV owner’s profit ($) ECOST ($) PV placement Opened switches
PSO 35.42 183.59 B13, B18, B26 L7−9, L9−10, L14−15, L18−33, L28−29
DA 51.99 181.46 B28, B32, B33 L7−8, L9−10, L14−15, L16−17, L28−29
Details are in the caption following the image
Power generation with PVs optimized with the DA in Case 4.

5.1.5. Case 5: MO Reconfiguration Aiming to Maximize PV Owner’s Profit and Minimize DisCo’s Cost

In this case study, the Pareto front is achieved for the recommended MO problem to maximize the PV owner’s profit and minimize DisCo’s cost at the same time. Table 8 also summarizes the Pareto results. As observed, the best trade-off result with the DA is related to solution#3, which is equal to 1.32. Moreover, the best trade-off outcome with the PSO is related to solution#7, which is equal to 1.28. For the best result in solution#3 with the DA, the PV systems can be installed at buses 21, 30, and 32, as depicted in Table 9. As seen, the reconfiguration can have a considerable effect on optimal PV placement. The PV owner’s profit, the DisCo’s cost, and the optimal reconfiguration optimized with the DA and PSO in this case study are also presented in Table 9. The injected power of PV systems optimized by the DA is given in Figure 8. As mentioned earlier, the proposed MO optimization approach can provide many economic and operational advantages for the players in the DN. It should be noted here that by achieving a trade-off between the PV owner’s profit and DisCo’s cost, the losses in the DN are also noticeably minimized inherently through DisCo’s cost, which is highly advantageous from DisCo’s perspective.

Table 8. Pareto optimal results in Case 5.
Solution# Ψ1($) Ψ2($) Sum (, )
DA result
 1 181.27 52.79 0.00 1.00 1.00
 2 180.80 51.75 0.38 0.82 1.20
 3 180.55 51.34 0.57 0.75 1.32
 4 180.55 51.28 0.58 0.74 1.32
 5 180.55 51.28 0.58 0.74 1.32
 6 180.51 50.95 0.61 0.68 1.29
 7 180.42 50.22 0.68 0.55 1.24
 8 180.40 50.15 0.69 0.54 1.23
 9 180.36 49.70 0.73 0.46 1.19
 10 180.36 49.70 0.73 0.46 1.19
 11 180.34 49.42 0.74 0.41 1.16
 12 180.28 49.21 0.79 0.38 1.17
 13 180.13 47.25 0.91 0.04 0.95
 14 180.13 47.24 0.91 0.04 0.95
 15 180.02 47.03 1.00 0.00 1.00
  • The best trade-off result.
Table 9. PV owner’s profit, DisCo’s cost, optimal location of PVs, and reconfiguration of IEEE 33-bus in Case 5.
Case 5 PV owner’s profit ($) Disco’s cost ($) PV placement Open switch
PSO 34.56 178.99 B12, B18, B24 L7−8, L10−11, L14−15, L17−18, L28−29
DA 51.34 180.55 B21, B30, B32 L10−11, L14−15, L16−17, L28−29, L8−21
Details are in the caption following the image
Power generation with PVs optimized with the DA in Case 5.

5.1.6. Case 6: MO Reconfiguration Aiming to Minimize DisCo’s Cost and ECOST

Here, the minimization of the cost of the DisCo and ECOST are considered and the Pareto front is attained for the proposed MO problem. Pareto optimal solution of the proposed model in Case 6 is summarized in Table 10, in which the best trade-off result is achieved in comparison with each SO problem. The min–max fuzzy satisfying technique is employed to attain the best trade-off result related to solution#9 with the DA, which is equal to 1.65. It is related to solution#6 with the PSO, which is equal to 1.49. For the best result in solution#9 with the DA, the PV systems are installed at buses 17, 18, and 31, as shown in Table 11. The ECOST, Disco’s cost, and the optimal configuration optimized with the DA and PSO are also presented in Table 11. The profit of PV owners is also equal to $28.6.

Table 10. Pareto optimal solutions of the suggested model in Case 6.
Solution# Ψ1 ($) Ψ2 ($) Sum (, )
DA result
 1 209.61 178.13 0.00 1.00 1.00
 2 191.08 178.27 0.52 0.96 1.47
 3 189.73 178.31 0.56 0.94 1.50
 4 188.90 178.63 0.58 0.84 1.42
 5 188.89 178.63 0.58 0.84 1.42
 6 188.89 178.63 0.58 0.84 1.42
 7 183.74 178.71 0.73 0.81 1.54
 8 181.66 178.79 0.78 0.79 1.57
 9 178.43 178.83 0.87 0.78 1.65
 10 176.81 179.29 0.92 0.63 1.55
 11 176.38 179.29 0.93 0.63 1.56
 12 175.22 179.70 0.96 0.50 1.46
 13 175.19 179.71 0.96 0.50 1.46
 14 174.91 181.08 0.97 0.06 1.03
 15 173.93 181.27 1.00 0.00 1.00
  • The best trade-off result.
Table 11. DisCo’s cost, ECOST, optimal placement of PVs, and reconfiguration in Case 6.
Case 6 DisCo’s cost ($) ECOST ($) PV placement Opened switches
PSO 178.81 180.16 B11, B25, B32 L7−8, L9−10, L14−15, L28−29, L32−33
DA 178.43 178.83 B17, B18, B31 L7−8, L10−11, L13−14, L27−28, L32−33

5.1.7. Case 7: MO Reconfiguration Aiming to Maximize PV Owner’s Profit, Minimize DisCo’s Cost, and ECOST

In this part, the Pareto front is attained for the offered MO problem to maximize the PV owner’s profit as well as to minimize DisCo’s cost and ECOST at the same time. Figure 9 displays the results of this case study. The Pareto solutions with DA are presented in Table 12. To select the greatest trade-off result, the min–max fuzzy satisfying method is used. As seen, the best trade-off result is achieved in solution#25, which is equal to 2.23. Table 13 depicts ECOST, DisCo’s cost, and the PV owner’s profit optimized using the DA and PSO. According to the table, the PV systems are installed at buses 26, 32, and 33, and L7−8, L10−11, L14−15, L28−29, and L18−33 are opened. The injected power of the PVs for Case 7 using the DA and PSO are presented in Figures 10 and 11, respectively. According to the results of the IEEE 33-bus DN, dealing with the problem of optimal reconfiguration and PV placement provides a more efficient schedule, as all players in the DN including DisCos, GenCos, and customers are fulfilled jointly. In addition, another important issue affecting PV owners and DisCo plans is the contract price of PV energy. The power loss reduction resulting from the optimal network configuration and PV capacities is calculated in this case to assess the degree of efficient operation of the network.

Details are in the caption following the image
Pareto optimal front of the MO problem in Case 7.
Table 12. Pareto optimal solutions of the model in Case 7.
Solution# Ψ1 ($) Ψ2 ($) Ψ3 ($) Sum (, , )
1 204.10 179.90 45.45 0.00 0.82 0.28 1.11
2 204.10 179.90 45.45 0.00 0.82 0.28 1.11
3 204.10 179.90 45.45 0.00 0.82 0.28 1.11
4 204.10 179.90 45.45 0.00 0.82 0.28 1.11
5 204.10 179.90 45.45 0.00 0.82 0.28 1.11
6 204.10 179.90 45.45 0.00 0.82 0.28 1.11
7 204.10 179.90 45.45 0.00 0.82 0.28 1.11
8 204.10 179.90 45.45 0.00 0.82 0.28 1.11
9 188.93 182.14 55.44 0.52 0.07 0.96 1.56
10 187.87 180.96 55.15 0.56 0.46 0.94 1.97
11 187.87 180.96 55.15 0.56 0.46 0.94 1.97
12 187.79 182.35 55.99 0.56 0.00 1.00 1.56
13 186.77 180.05 48.08 0.60 0.77 0.46 1.83
14 185.92 180.31 49.39 0.63 0.68 0.55 1.86
15 185.92 180.31 49.39 0.63 0.68 0.55 1.86
16 185.92 180.31 49.39 0.63 0.68 0.55 1.86
17 182.26 180.43 50.68 0.75 0.64 0.64 2.04
18 182.26 180.43 50.68 0.75 0.64 0.64 2.04
19 182.26 180.43 50.68 0.75 0.64 0.64 2.04
20 181.29 180.58 51.63 0.79 0.59 0.70 2.08
21 181.29 180.58 51.63 0.79 0.59 0.70 2.08
22 179.74 180.81 53.01 0.84 0.52 0.80 2.15
23 179.68 180.89 54.14 0.84 0.49 0.87 2.21
24 179.68 180.89 54.14 0.84 0.49 0.87 2.21
25 176.82 180.51 51.19 0.94 0.61 0.67 2.23
26 176.20 180.96 51.99 0.96 0.46 0.73 2.15
27 175.96 180.53 50.77 0.97 0.61 0.65 2.23
28 175.96 180.53 50.77 0.97 0.61 0.65 2.23
29 175.96 180.53 50.77 0.97 0.61 0.65 2.23
30 175.10 179.37 41.26 1.00 1.00 0.00 2.00
  • The best trade-off result.
Table 13. ECOST, DisCo’s cost, PV owner’s profit, the optimallocation of PVs, and reconfiguration of IEEE 33-bus in Case 7.
Case 7 ECOST ($) DisCo’s cost ($) PV owner’s profit ($) DG placement Opened switches
PSO 177.86 179.05 36.58 B15, B20, B30 L7–8, L9–10, L14–15, L28–29, L18–33
DA 188.93 182.14 55.44 B26, B32, B33 L7–8, L10–11, L14–15, L28–29, L18–33
Details are in the caption following the image
Power generation with PVs optimized with the PSO in Case 7.
Details are in the caption following the image
Power generation with PVs optimized with the DA in Case 7.

The variation of active power loss of the test system in all scenarios for this case is depicted in Figure 12. As can be seen in this case, when a trade-off is achieved among the PV owner’s profit, DisCo’s cost, and ECOST, power losses of the network is minimized significantly. For better assessments, all considered indexes for optimization and the standard deviation (std) of the voltages in all cases using the DA are provided in Table 14. It is obvious from the results that this problem can be addressed as a multi-objective problem that considers the benefits of all players in the DN. Moreover, using the proposed optimization approach, the standard deviation of the voltage is reached to one per unit compared with without using the proposed approach.

Details are in the caption following the image
Active power loss of network in all scenarios for Case 7.
Table 14. Comparison indexes in all scenarios.
Scenario S1 S2 S3 S4 S5 S6 S7
ECost ($) 178.574 213.495 154.216 181.464 195.991 178.434 181.516
Disco ($) 181.711 177.369 186.551 180.877 180.551 178.831 180.474
DG owner ($) 59.750 11.375 55.901 51.992 51.344 28.610 50.841
Power loss (MW) 0.132 0.132 0.243 0.127 0.124 0.125 0.124
Voltage std 0.017 0.016 0.027 0.017 0.016 0.017 0.017

5.2. Real DN

In this part, the suggested model is applied to a real DN in Iran. The real distribution network is shown in Figure 13. The name of the right-side feeder with red color is #518 and the left side with blue color is #512. For this case study, three PV systems are permitted to be installed in the DN, each with a rated capacity of 1 MW. The Pareto front is achieved for the suggested model to optimize the PV owner’s profit, minimizing DisCo’s cost, and ECOST. Figure 14 shows the Pareto optimal front achieved for this case study. Table 15 illustrates the Pareto results. As seen, the best trade-off results are attained using the DA in solution#9, which is equal to 2.3. Table 16 presents the values of the ECOST, Disco’s cost, and PV owner’s profit before PV installation and reconfiguration as well as after optimal reconfiguration and PV allocation using the DA. The power generation of PV systems in the real DN is shown in Figure 15. The optimal placement of PVs and optimal reconfiguration of DN in real system are also depicted in Figure 16. The variation of active power loss of the real DN in all scenarios is shown in Figure 17. As seen, when a compromise is attained among all players in the DN, power losses of the system is reduced considerably. Table 17 also compares the amount of load, losses, maximum loading, and minimum voltage before and after optimization in two considered feeders.

Details are in the caption following the image
The real test network: (a) the GIS view and (b) the one-line diagram of feeders.
Details are in the caption following the image
The real test network: (a) the GIS view and (b) the one-line diagram of feeders.
Details are in the caption following the image
Pareto optimal front of MO problem in the real DN.
Table 15. Pareto optimal solutions of the proposed model for real DN.
Solution# Ψ1 ($) Ψ2 ($) Ψ3 ($) Sum (, , )
DA result
 1 35.99 260.79 29.90 0.80 0.99 0.00 1.79
 2 35.87 261.48 39.86 0.81 0.66 0.50 1.97
 3 35.76 262.18 49.83 0.82 0.31 1.00 2.14
 4 43.71 261.48 29.90 0.16 0.66 0.00 0.81
 5 45.37 262.13 39.86 0.02 0.34 0.50 0.86
 6 45.21 262.81 49.83 0.03 0.01 1.00 1.04
 7 35.27 260.82 29.90 0.86 0.97 0.00 1.84
 8 35.15 261.50 39.86 0.87 0.64 0.50 2.02
 9 33.63 262.20 49.83 1.00 0.30 1.00 2.30
 10 45.43 262.15 39.86 0.01 0.33 0.50 0.84
 11 45.59 261.49 29.90 0.00 0.65 0.00 0.65
 12 35.95 260.76 29.90 0.81 1.00 0.00 1.81
 13 35.82 261.45 39.86 0.82 0.67 0.50 1.99
 14 34.26 262.15 49.83 0.95 0.33 1.00 2.28
 15 45.28 262.83 49.83 0.03 0.00 1.00 1.03
  • The best trade-off result.
Table 16. ECOST, Disco’s cost, and PV owner’s profit for real DN.
Real DN case ECOST DisCo’s cost PV owner’s profit
Before optimization 46.217 259.643 0
DA 33.632 262.202 49.826
Table 17. Comparison of the indexes in two considered feeders before and after optimization.
Feeder name Load (MW) Losses (kW) Max line loading (%) Min voltage (p.u.)
Before optimization
 #518 2.30 67 86 0.957
 # 512 3.16 126 92 0.943
After optimization
 #518 3.419 65 82 0.964
 #512 2.043 52 87 0.957
Details are in the caption following the image
Power generation with PVs optimized with the DA in the real DN.
Details are in the caption following the image
Optimal location of PVs and reconfiguration in the real DN.
Details are in the caption following the image
Active power loss of the real DN in all scenarios with the DA.

6. Conclusion

A MO stochastic model for PV placement and reconfiguration of DNs at the same time is proposed in this paper. The model is investigated on a standard test system and a areal DN in the Iran power market from GenCo’s point of view in which the profit of PV owners are maximized. It is also evaluated from DisCo’s point of view in which the total cost of power procurementis minimized and also assessed from the customer’s perspective in which the ECOST is minimized. The mentioned objectives are satisfied by considering the operational and physical limitations of the DN. To achieve more practical results, the uncertainties of PV systems, electricity prices, and demands are modeled using the scenario approach. To solve the suggested model, the DA is employed. The performance of the DA in all case studies is compared with the PSO. The fuzzy satisfying criterion is also used to find the best compromise solution. The DA is very simple and easy to implement and shows reasonable performance to optimize various problems in different areas. Furthermore, having few parameters for tuning is another advantage of DA. Moreover, the convergence time of the algorithm is reasonable. This study is expected to be a beneficial reference for researchers and engineers involved in deregulated power distribution systems.

Abbreviations

  • ENS:
  • Energy not supplied
  • DA:
  • Dragonfly algorithm
  • PV:
  • Photovoltaic
  • PSO:
  • Particle swarm optimization
  • DN:
  • Distribution network
  • ECOST:
  • Expected interruption cost
  • GenCos:
  • Generating companies
  • DER:
  • Distributed energy resource
  • DisCos:
  • Distribution companies
  • MILP:
  • Mixed-integer linear programing
  • SO:
  • Single-objective
  • DG:
  • Distributed generation
  • MO:
  • Multi-objective
  • PDF:
  • Probability density function.
  • Conflicts of Interest

    The authors declare that there are no conflicts of interest regarding the publication of this paper.

    Authors’ Contributions

    Mohammad Najafi and Mohammad Reza Miveh contributed equally to this manuscript.

    Data Availability

    All data used to support the findings of this study are available from the corresponding author upon request.

      The full text of this article hosted at iucr.org is unavailable due to technical difficulties.