Study on Presplitting Blasting the Roof Strata of Adjacent Roadway to Control Roadway Deformation
Abstract
In order to solve the problem of roadway deformation based on the theory of “short cantilever beam by roof cutting,” the method of “pressure relief by roof cutting in the adjacent roadway” is proposed. Through presplitting blasting the roadway hard rock layer, the stress propagation path is cut off, and the surrounding rock stress environment of the roadway is improved, to achieve the purpose of controlling the deformation of the roadway caused by stress. Through theoretical analysis, it is determined that the depth of the presplitting blasthole is 17 m, and the angle with the vertical direction is 10°. Based on in situ measurements and tests, by presplitting blasting the roof strata of the adjacent roadway, the maximal value of the working resistance of the hydraulic support in the presplitting blasting side of the working face decreased by 24.9%, and the average volumes of the maximum floor heave, the maximum roof subsidence, and the maximum ribs displacement were reduced by 50.1%, 34.9%, and 41.7%, respectively. This method completely changes the traditional thought patterns of “reinforcing support” to control roadway deformation from “strong support” to “pressure relief.” It provides a new idea for controlling the roadway deformation.
1. Introduction
A protective coal pillar of 10∼30 m should be left between adjacent working faces to prevent the roadway from deformation and damage in traditional long wall mining [1–3]. As the depth of mining continues to increase, the surrounding rock of the roadway gradually exhibits the characteristics of soft rock under the influence of high ground stress, high ground temperature, high osmotic pressure, and strong mining disturbance [4–7]. The velocity and time of creep are greater than those of shallow rock strata [8, 9]. The roadway deformation increases significantly during mining, and the floor heave is especially severe. The roadway deformation not only affects pedestrians, transportation, and ventilation but also causes the entire roadway to be scrapped in serious cases, which seriously affects the safety of mining. The roof and ribs of roadways in China are usually supported by “bolt/cable + mesh,” while the floor is usually unsupported. Although the protective coal pillar is left, the floor heave is still the most serious problem in roadway deformation. At present, generally, the methods of undercutting the floor, reinforcement, or pressure relief are used to control the floor heave [10–12].
In 2008, the “short cantilever beam by roof cutting” theory [13–16] was put forward by Professor Manchao He, an academician of the Chinese Academy of Sciences. In this theory, the ground pressure is used for the purpose of advancing the roof caving by precutting to form a cantilever beam above the gob-side gateway. When the precutting is performed on the roof of the gateway, the transmission of overburden pressure is cut off, which mitigates the ground pressure on the roadway. Also, part of the roof rock mass is driven down and fills the gob in time to support the overlying rock strata, reduce the suspension area, and reduce the influence on the roadway.
Based on this theory, this study proposes the method of “pressure relief by roof cutting in the adjacent roadway” to control roadway deformation. The purposes of presplitting blasting the roof strata of the adjacent roadway are to cut off the stress propagation path and to improve the surrounding rock stress conditions of the roadway to control the roadway deformation [17–20]. As shown in Figure 1, rock B and rock C are the main roof above the gob of the adjacent roadway, which is driven by overburden pressure. Rock A is the main roof above the coal pillar and roadway. When the adjacent working face is mined, since part of the roof strata of the adjacent roadway has been cut off, rock A is completely separated from rock B, which mitigates the influence of rock B and rock C on the roadway when they collapse, and the transmission of overburden pressure is cut off. This achieves the purpose of reducing the deformation of the surrounding rock and protecting the roadway.

This study chose the 72909 ventilation roadway of the Du’erping coal mine in Shanxi Province in China as the engineering background to verify the effect of roadway deformation control by presplitting blasting the roof strata of the adjacent roadway. As shown in Figure 2(a), the Du’erping coal mine (Xishan Coal Electricity Group Co., Ltd.) is in Taiyuan city in China’s Shanxi Province, and the location of the 72909 ventilation roadway is shown in Figure 2(b).


2. Influenced Factors of Roadway Deformation
Ground stresses, the strength of the surrounding rock, and the support of the roadway are the most important factors that affect the stability of the roadway surrounding rock [21–24]. The roof and ribs of the roadways in China are usually supported by “bolt/cable + mesh,” while the floor is usually unsupported, and the floor heave is common; therefore, this research focused on the influence of ground stress and floor lithology on the floor heave. According to references [25, 26], the rising and compressing coal rock layers are distributed from the floor to the deep, and the dividing point of the rising and compressing coal rock layers is the zero-displacement point; the tensile strain and compressive strain coal strata are distributed from the floor to the deep, and the dividing point of the tensile strain and compressive strain coal stratum is the zero-strain point. With the zero-displacement point and zero-strain point as the boundary, the floor strata are divided into tensile strain rise zone, tensile strain compression zone, and compressive strain compression zone. Figure 3(a) demonstrates the influence of floor lithology on the floor heave when the other factors are fixed. The mechanical parameters of floor lithology are shown in Table 1. (1) As the floor strength decreases, the zero-displacement point and zero-strain point develop toward the depth of the floor. (2) When the floor is hard or medium-hard rock, as the floor lithology changes, the changes in the zero-displacement point and the zero-strain point are small, and the variation ranges are 0.30–0.57 m and 2.57–2.80 m, respectively. (3) When the floor is soft or extremely soft rock, as the floor lithology changes, the zero-displacement point and zero-strain point are transferred quickly and deeply into the floor, the zero-displacement point changes from 1.10 m to 2.95 m, and the zero-strain point changes from 3.13 m to 5.67 m. Figure 3(b) demonstrates the influence of horizontal stress on the floor heave when the other factors are fixed. (1) The critical point of the coefficient of horizontal pressure is 1.8 when the coefficient of horizontal pressure is less than 1.8, and the change in the zero-stain point is small. Otherwise, the zero-stain point increases significantly. (2) With the increase in horizontal stress, the zero-displacement point has basically a linear increase.


Mechanical parameter | Hard rock | Medium-hard rock | Soft rock | Extremely soft rock |
---|---|---|---|---|
Compressive strength (MPa) | ≥60 | 30∼60 | 15∼30 | ≤15 |
Cohesion (MPa) | ≥6.5 | 4.0∼6.5 | 2.5∼4.0 | ≤2.5 |
Internal friction angle (°) | ≥38 | 30∼38 | 20∼30 | ≤20 |
Strength of extension (MPa) | ≥4.2 | 3.2∼4.2 | 2.2∼3.2 | ≤2.2 |
Density (g·m−3) | ≥2.4 | 2.0∼2.4 | 1.6∼2.0 | ≤1.6 |
As shown in Figure 3, the rock strength of the surrounding rock and the magnitude of ground stress all have a great influence on the surrounding rock deformation of the roadway. At present, the methods of reinforced support or grouting in the surrounding rock are based on increasing the strength of the surrounding rock. However, the control effect of the surrounding rock deformation is poor, particularly in a roadway with high ground stress. So, this study proposes the method of presplitting blasting the roof strata of the adjacent roadway to control roadway deformation. The purpose of controlling the surrounding rock deformation is achieved by roof cutting to relieve the mining pressure.
3. Engineering Background
3.1. General Situation of the Working Face
The 72909 working face is located in panel South-9, the primary mineable coal bed is the #2 coal seam, the mining depth of the #2 coal seam is 505–647 m, the average thickness is 2.93 m, and the dip angle is 6°. The strike length and the working face length of 72909 are 1595 m and 216 m, respectively. The surrounding rock of the 72909 ventilation roadway is mainly composed of mudstone and sandstone, and the detailed strata histogram is shown in Figure 4.

3.2. Geomechanical Test of Roadway Surrounding Rock
3.2.1. Layout of Measure Points
In order to obtain an overall understanding of the geological mechanics of the surrounding rock of the #2 coal seam, a total of three measuring points was arranged on the site. To ensure whether the test was accurate and representative, the selection of the measuring points followed the principles: (1) large tectonic zones were avoided; (2) the rock strata for the test was relatively intact; (3) measuring points maintained a certain distance; (4) the systems of ventilation, water, power, and transportation were complete; and (5) the height and width of the roadway met the requirements for drilling. As shown in Figure 5, the first measuring point was located in the South-9 mine haulage roadway, the second measuring point was located in the South-9 haulage roadway, and the third measuring point was arranged in the 72909 ventilation roadway.

3.2.2. Roof Strata Distribution and Structure Observation
The purpose of observing the structure of the surrounding rock is to understand the distribution of roof strata within 25 m and to determine a suitable test section for stress measurement. The borehole observations are shown in Figure 6, and the analysis results are shown in Table 2.



Measuring points | The suitable test section for stress measurement |
---|---|
The first measuring point | The 17 m position conforms to the experimental conditions |
The second measuring point | The 21 m position conforms to the experimental conditions |
The third measuring point | The 14.7 m position conforms to the experimental conditions |
3.2.3. Ground Stress Measurement
- (1)
The hydraulic fracturing curve of the first measuring point is shown in Figure 7(a).



- (2)
The hydraulic fracturing curve of the second measuring point is shown in Figure 7(b).
- (3)
The hydraulic fracturing curve of the third measuring point is shown in Figure 7(c).
According to the measurements on the site, the surrounding rock of the #2 coal seam in the Du’erping coal mine is in a high stress field. The maximum and minimum values of the maximum horizontal principal stress are 33.62 MPa and 31.50 MPa, respectively. The maximum and minimum values of the minimum horizontal principal stress are 20.60 MPa and 13.14 MPa, respectively. The maximum and minimum values of the vertical stress are 30.16 MPa and 25.22 MPa, respectively. The type of stress field is σH > σv > σh.
3.2.4. The Strength of the Floor Strata Measurement
The borehole penetrating method was used to measure the surrounding rock strength of the floor strata in the 72909 ventilation roadway. Compared with the method of testing the strength of rock samples in laboratory, the borehole penetrating method can measure not only the rock strength of different depths in floor strata but also the rock layers containing structural planes, such as joints and cracks [27, 28]. Therefore, the measured rock mass strength is more accurate and closer to the actual situation. The rock strength of the rock layers was measured within 10 m of the floor with the WQCZ-56 surrounding rock strength tester. The test results of the surrounding rock strength of the #2 coal seam floor strata are shown in Figure 8.

A comprehensive analysis of the strength test results of the floor strata showed that the floor strata of #2 coal seam in the Du’erping coal mine is mainly mudstone, sandy mudstone, and fine sandstone, and some sandy mudstone rock layers also contain fine sandstone interlayers. Due to the diagenetic process, the thickness of the rock layer is different in different measuring point locations. The strength of the mudstone layer is concentrated at 30–45 MPa, and the average value is 34.22 MPa. The strength of the sandy mudstone layer is concentrated at 45–65 MPa, and the strength is obviously higher than the rock layer at the same depth—the fine sandstone interlayer. The average strength of the sandy mudstone layer is 57.52 MPa, and the average strength of the fine sandstone layer is 80.79 MPa.
3.3. Main Reason for the Floor Heave in the 72909 Ventilation Roadway
According to the hydraulic fracturing experiment, the surrounding rock of the #2 coal seam in the Du’erping coal mine is a high stress field, and the type of stress field is σH > σv > σh. According to the strength of the floor strata measurement, the floor strata of the 72909 ventilation roadway are mainly hard rock and medium-hard rock, and there is almost no water in the roadway; therefore, the softening effect of water on the floor strata of the roadway is negligible. The ground stress is the main reason for the floor heave in the 72909 ventilation roadway.
4. Scheme Design for Pressure Relief by Roof Cutting
The essence of pressure relief by roof cutting is the blasting presplitting of the roof strata of the adjacent roadway by the bidirectional energy-cavity blasting technology. After the adjacent working face is mined, the roof strata of the adjacent roadway are cut by the ground pressure. The blasting presplitting cuts the connection in the roof strata between the adjacent working face and the protected roadway, reducing the impact of ground pressure on the protected roadway. Moreover, the fallen gangue supports the overlying main roof strata, controls the rotation and sinking deformation of the main roof strata, and realizes the purpose of pressure relief. Based on the existing research results and field engineering experience [29–31], the height and angle of the roof cutting have a great influence on the effect of pressure relief. A reasonable roof cutting height can completely cut off the roof strata connection between the protected roadway and the gob of the adjacent working face, ensuring that the adjacent working face will not have a great impact on the protected roadway. A reasonable angle of roof cutting can also ensure that the roof strata of the adjacent roadway collapse in time, filling in the gob after the working face is mined and supporting the overlying rock strata to mitigate the impact of the main roof sagging on the protected roadway. The depth and angle of the roof cutting have a great influence on the effect of pressure relief. Therefore, the optimal depth and angle of the roof cutting are key to the “pressure relief by roof cutting in the adjacent roadway” to control roadway deformation.
4.1. Reasonable Design of Roof Cutting Height
- (1)
The location of the hard overlying strata.
According to the observations of the roof strata and geological data, there are about eight overlying strata within 25 m of the #2 coal seam.
When (qn)1 < (qn−1)1, the nth overlying layer is the first hard stratum. Then, the load of the overlying layer on the nth overlying layer was calculated with the nth overlying layer as the basal layer. Ultimately, the calculations and analyses determined all the hard overlying strata within 25 m of the #2 coal seam.
The above analysis shows that there are three hard rock layers within 25 m above the #2 coal seam. The third hard overlying layer is fine sandstone with a thickness of 7.87 m, and it is away from the #2 coal seam 8.5 m, as shown in Table 3.
Location | Lithology | Thickness (m) | Remark |
---|---|---|---|
8 | Sandy mudstone | 3 | |
7 | Mudstone | 1.39 | |
6 | Sandy mudstone | 4.91 | |
5 | Fine sandstone | 7.87 | The third hard overlying layer |
4 | Sandy mudstone | 4.25 | The second hard overlying layer |
3 | 1# coal seam | 0.5 | |
2 | Fine sandstone | 1.75 | The first hard overlying layer |
1 | Siltstone | 1.94 |
- (2)
The thickness of the overlying strata collapse to fill the gob.
To verify the aforementioned calculation results according to the field conditions of the #2 coal seam of the Du’erping coal mine, the following field parameters applied to equation (9) were chosen: Hm = 3.5 m and K = 1.35. In order to obtain the maximum value of the height of roof cutting, the volumes of roof convergence and floor heave were not taken into consideration, i.e., ΔH1 = ΔH2 = 0. The height of roof cutting was 10 m, which was calculated using equation (9).
In accordance with the aforementioned analysis, the optimal theoretical height of roof cutting is 17 m, not only to cut off the stress transfer but also to ensure that the gob can be filled with the collapsed gangue.
4.2. The Angle of Roof Cutting and Roadway Support
In order to prevent unstable failure of the roof strata of the 72908 haulage roadway after presplitting blasting, the presplitting blasting hole needs to be an angle “α” to ensure that the roof can self-lock and maintain stability after presplitting blasting, but the angle “α” should not be too large to avoid affecting the collapse of the overlying strata. Meanwhile, single props were used in the temporary support and were set at the presplitting blasting side, and the interval of two props was 1000 mm, as shown in Figure 9(a).


For convenient calculation, a component of T can be approximated as f where “f = T sin α”. According to the actual conditions of the 72908 haulage roadway, the field parameters were chosen as follows: φ = 27°, τ = 0.13 MPa, ρ = 2500 kg/m3, h = 17 m, and d = 4.2 m.
According to the aforementioned theoretical calculation, when the angle of the presplitting blasting borehole is in the range of 10° to 15°, the roof strata of the roadway can remain stable. The smaller the angle of the presplitting blasting borehole is, the smaller the drilling depth required to cut off the hard rock layer is, the smaller the amount of work is, and the easier it is for the roof strata to fall. Thus, the angle of the presplitting blasting borehole was set at 10°. Under this condition, the working resistance of a single prop was about 180 kN, and a row of single props set at the presplitting blasting side was able to meet the requirements for stability maintenance of the roof strata.
4.3. Numerical Simulation
A numerical model was established according to the geological conditions of the #2 coal seam in the Du’erping coal mine. The mechanical parameters of the roof and floor rock strata are shown in Figure 3. The model length, width, and height were 565 × 300 × 60 m; the vertical boundary force was applied to the upper boundary; the lower boundary was fixed in the vertical direction; and the front, rear, left, and right boundaries were fixed in the horizontal direction. The width of the simulated working face was 212 m, the thickness of the coal seam was 2.0 m, and the width and height of the roadway were 4.0 × 2.0 m. A 25 m protective coal pillar was placed between the 72909 working face and the 72908 working face. After the 72908 working face was mined, the horizontal section of the vertical stress distribution of the 72909 working face at 20 m was determined and is shown in Figure 10. The roof strata of the 72908 haulage roadway without presplitting blasting is shown in Figure 10(a), and the roof strata of the 72908 haulage roadway with presplitting blasting is shown in Figure 10(b).


Figure 10 shows whether presplitting blasting the roof strata of the 72908 haulage roadway had a great influence on the stress distribution of the surrounding rock. As shown in Figure 10(a), for the roof strata of the 72908 haulage roadway without presplitting blasting, the 72908 haulage roadway and 72909 ventilation roadway both had a concentration of stress in the ribs. The maximum values of stress in the coal pillar side and working face side of the 72909 ventilation roadway were 30.1 MPa and 31.5 MPa, respectively. As shown in Figure 10(b), for the roof strata of the 72908 haulage roadway with presplitting blasting, there was almost no stress concentration in the coal pillar, and the stress concentration transferred to the depth of the working face coal mass. The maximum values of stress in the coal pillar side and working face side of the 72909 ventilation roadway were 16.8 MPa and 18.3 MPa, respectively. After presplitting blasting the roof strata, the maximum value of stress in the coal pillar side and working face side of the 72909 ventilation roadway were reduced by 44.2% and 41.9%, respectively.
As shown in Figure 10, at about 20 m in front of the 72909 working face, a concentration of stress occurred in the two ribs of the 72909 ventilation roadway. Therefore, the vertical section of the vertical stress was selected 20 m ahead of the 72909 working face. The vertical section of the vertical stress for the roof strata of the 72908 haulage roadway without presplitting blasting is shown in Figure 11(a), and the roof strata of the 72908 haulage roadway with presplitting blasting is shown in Figure 11(b).


As shown in Figure 11(a), the stress concentration was about 5 m in the working face side of the 72909 ventilation roadway, the maximum value of stress was 29.8 MPa, and the maximum value of stress in the coal pillar side was 17.5 MPa. As shown in Figure 11(b), since the presplitting blasting cuts off the stress propagation path, the stress concentration area of the 72909 ventilation roadway was transferred to the depth of the working face coal mass. The maximum value of stress in the working face side was 15.5 MPa, and the maximum value of stress in the coal pillar side was 12.4 MPa; these were reduced by 47.9% and 29.1%, respectively.
As shown in Figure 1, when the presplitting blasting was carried out on the roof strata of the adjacent roadway, the hard overlying strata were cut off, and the roof strata fell and filled the gob, which could have supported the overlying strata and reduced the disturbance of mining to the roadway.
According to the above analysis, roof cutting in the adjacent roadway cut off the stress propagation path; thus, the stress concentration was forced to transfer to the deep part of the coal mass, so the surrounding rock stress of the roadway was reduced, and the mechanical environment of the surrounding rock of the roadway was improved. The problem of roadway deformation caused by stress was fundamentally solved. Therefore, in theory, the presplitting blasting of the roof strata of the adjacent roadway can improve the stress of the surrounding rock of the roadway and reduce the stress of the surrounding rock, so that the size of the protective coal pillar between the working faces reduces, improving the coal recovery rate and reducing resource waste.
5. Determination of the Best Blasting Parameters
In order to verify the effect that roof cutting in the adjacent roadway to control the roadway deformation, 300 m of the 72908 haulage roadway was selected as the test section, and it was divided into three sections along the driving direction of the working face—each section is 100 m long. As seen in Figure 12(a), the first section was the comparison section without presplitting blasting, the second section was the transitory section used to determine the best blasting parameters, the third section was the experimental section with presplitting blasting with the best blasting parameters. The presplitting blasting of the overlying strata on the 72908 haulage roadway is shown in Figure 12(b).


According to previous engineering experience [33–35], the space between the presplitting blasting borehole is generally in the range of 400–600 mm. The numerical simulation was carried out on the rock strata conditions of the #2 coal seam in Du’erping coal mine. The LS-DYNA software was used to numerically analyze the presplitting blasting borehole spaces of 400 mm, 500 mm, and 600 mm to determine the optimal space of the borehole. The results are shown in Figure 13.



As shown in Figure 13, when the space between the presplitting blasting borehole was 400 mm, the stress superposition was too strong and easily caused the borehole to collapse. When the space between the presplitting blasting borehole was 500 mm, the stress superposition was strong enough to run through the roof strata. When the space between the presplitting blasting borehole was 600 mm, the stress superposition was too feeble to run through the roof strata. Based on the numerical simulation, considering the previous engineering experience and engineering quantity, the space between the presplitting blasting borehole was selected to be 500 mm.
In order to ensure the effect of presplitting blasting, a selection of 100 m in the 72908 haulage roadway was chosen to be the transitory section for the blasting experiment and the optimum blasting parameters were selected. According to the aforementioned analysis, the presplitting blasting borehole had an interval of 500 mm, a length of 17 m, and an angle with the vertical direction of 10°. The length of the binding energy tube was 1.5 m, and each presplitting blasting borehole had nine binding energy tubes. The length of the lute was 3.5 m. The experimental schemes for the blasting experiment are shown in Table 4. The experimental schemes for the blasting methods are shown in Figure 14.
Scheme | Volume of explosives | Blasting method |
---|---|---|
1 | 3 + 3 + 3 + 3 + 3 + 2 + 2 + 2 + 1 | Single-borehole blasting interval one hole |
2 | 4 + 3 + 3 + 3 + 3 + 2 + 2 + 2 + 1 | Double-borehole blasting interval one hole |
3 | 4 + 4 + 3 + 3 + 3 + 2 + 2 + 2 + 1 | Three-borehole blasting interval one hole |
4 | 4 + 4 + 3 + 3 + 3 + 2 + 2 + 2 + 2 | Four-borehole blasting interval one hole |
5 | 4 + 4 + 3 + 3 + 3 + 2 + 2 + 2 + 2 | Five-borehole blasting interval one hole |





The observations of the blasting effect are shown in Figure 15. As shown in Figures 15(a)–15(c), in schemes 1–3, there were almost no crevices in the observant borehole. As shown in Figure 15(d), in scheme 4, there were a few crevices in the observant borehole. As shown in Figure 15(e), in scheme 5, there were many crevices throughout the observant borehole. Thus, the optimum blasting parameters were those in scheme 5, the optimum charge structures are shown in Figure 16, and the optimum blasting method is shown in Figure 14(e).






6. Engineering Application
Based on the design scheme, a 300 m section in the 72908 haulage roadway was chosen as the test section. In order to ensure the roadway deformation was adequate, the test section was from the open cut to 100–400 m, the presplitting blasting borehole was on the pillar side of the 72908 haulage roadway, and the length and angle of presplitting blasting borehole were set as 17.0 m and 10°, respectively. The division of the test section in the 72909 ventilation roadway was in accordance with the test section divided in the 72908 haulage roadway. The comparison section was from the open cut to 100–200 m, the transitory section was from the open cut to 200–300 m, and the experimental section was from the open cut to 300–400 m. In order to analyze the effect of pressure relief by roof cutting the adjacent roadway to control roadway deformation, the working resistance of the hydraulic support of 72909 working face and the volume of the roadway deformation of the 72909 ventilation roadway were monitored on the site. The layout of monitoring points is shown in Figure 17(a). At both ends and in the middle of the working face, five measuring points were set and recorded as the upper station, middle station, and lower station, respectively. In order to research the effect of pressure relief by presplitting blasting the roof strata of the adjacent roadway, we focused on the monitoring curve of the upper station, as shown in Figure 17(b). In the 72909 ventilation roadway, twelve monitoring points were set to monitor the volume of roadway deformation, and every 25 m, a monitoring point was set. The monitoring curves of the floor heave, roof subsidence, and rib displacement are shown in Figures 17(c)–17(e), respectively.





As seen in Figure 17(b), in the comparison section, the maximal working resistance of the hydraulic support was 36.5 MPa; in the transitory section, the maximal working resistance of the hydraulic support was 32.1 MPa; and in the experimental section, the maximal working resistance of the hydraulic support was 27.4 MPa. Compared with the comparison section, the pressure peaks of the transitory section and experimental section were reduced by 12.1% and 24.9%, respectively. The effect of pressure relief was obviously shown by cutting off the roof of the adjacent roadway. As shown in Figure 17(c), the average volumes of the maximum floor heave in the comparison section, transitory section, and experimental section were 505 mm, 383 mm, and 252 mm, respectively. Compared with the comparison section, the average volumes of the maximum floor heave in the transitory section and experimental section were reduced by 24.2% and 50.1%, respectively. As shown in Figure 17(d), the average volumes of the maximum roof subsidence in the comparison section, transitory section, and experimental section were 238 mm, 205 mm, and 155 mm, respectively. Compared with the comparison section, the average volumes of the maximum roof subsidence in the transitory section and experimental section were reduced by 13.9% and 34.9%. As shown in Figure 17(e), the average volumes of the maximum ribs displacement in the comparison section, transitory section, and experimental section were 283 mm, 218 mm, and 165 mm, respectively. Compared with the comparison section, the average volumes of the maximum rib displacement in the transitory section and experimental section were reduced by 22.9% and 41.7%, respectively. Based on in situ measurements and tests, cutting off the roof of the adjacent roadway controlled the roadway deformation satisfactorily.
7. Conclusions
The surrounding rock of the #2 coal seam in the Du’erping coal mine is in a high stress field, and the ground stress is the main reason for the roadway deformation of the 72909 ventilation roadway.
This study proposes a new method to control the roadway deformation caused by high ground stress. Presplitting blasting the hard roof strata of the adjacent roadway to cut off the stress propagation path to reduce the stress on the protected roadway and encourages the roof strata to fall down and fill the gob, reducing the disturbance from the collapse of the roof strata to the surrounding rock of the protected roadway. This achieves the purpose of controlling the deformation of the roadway.
Based on in situ measurements and tests, the effect of presplitting blasting the roof strata of the adjacent roadway on the roadway deformation caused by high ground stress is significant and provides a successful experience for other coal mines.
Conflicts of Interest
The authors declare no conflicts of interest.
Authors’ Contributions
Chaowen Hu, Xiaojie Yang, and Manchao He were responsible for conceptualization of the study; Chaowen Hu was responsible for methodology; Chaowen Hu and Yubo Zhou were responsible for software; Chaowen Hu and Haohao Wang performed the formal analysis; Chaowen Hu and Enze Zhen investigated the study; Chaowen Hu, Yubo Zhou, and Haohao Wang involved in data curation; and English editing was done by Xiaoyu Liu and Xingen Ma.
Acknowledgments
This work was supported by the National Natural Science Foundation of China (No. 41672347) and the Natural Science Foundation of Beijing (No. 8142032), which are gratefully acknowledged.
Open Research
Data Availability
All data included in this study are available upon request by contact with the corresponding author.